Building Main |
Essentially the building should be complete in the following areas before
the Building Safety Division can conduct a Final Inspection.
|
RESIDENTIAL |
COMMERCIAL |
|
Smoke Detectors |
Sprinklers Operative |
|
Water - Hot & Cold |
Fire Alarms Operative |
|
Plumbing Fixtures Installed |
Plumbing Fixtures Installed |
|
Electrical Outlets Installed |
Exit Signs |
|
Light Fixtures Installed or Blanked-Off |
Emergency Lights Operative (if required) |
|
Heating/Cooling System Operational |
Exit Door Hardware Installed |
|
Address on Building* |
Accessibility Items Installed such as:
|
|
Roofing/Siding Complete
Exterior Finishes |
Address on Building visible from street |
|
Driveway Installed |
Water - Hot & Cold |
|
Grading |
Fire Rated Doors Installed (if required) |
|
Stucco/EIFS Reports Submitted |
Fire Extinguishers Installed |
|
Required Special Reports*
-
Engineers letters, etc.
-
Backflow Prevention Reports
-
Landscape & Grading Certificates
-
Setback and Elevation Form
|
Landscaping & Grading |
|
|
Parking lots installed and striped with
lights and directional signs |
|
*those items in residential and
commercial. |
Heating/Cooling Systems Operational |
Some Items such as Landscaping, Parking Lots, and Parking Lot Striping,
Back-ordered Fixtures, etc. may be omitted but only
with special permission from the appropriate authority such as the Building Official, Fire Chief, City Engineer, Current Planning Manager,
Community Services Director, etc.
The
Owner/Contractor is responsible for contacting the appropriate departments
for final inspection through the Building Division inspection line.
These must be signed off by all appropriate divisions/departments before a
Certificate of Occupancy can be issued.
Inspection requests should only be made when the job is ready for inspection
and are accepted each business day. Inspectors cannot take inspection
requests in the field.
All
inspections must be scheduled the business day preceding the scheduled
inspection request. Please speak slowly and clearly. We
apologize, but we cannot accept specific times for inspections, except for
concrete placement, temporary and permanent electrical meter sets UFER
ground in foundation.
Note: It is highly recommended that the requests be called
in on a "land line" since cellular phone connections are not reliable and
the request may not be recorded. If you are unsure of any of these
requirements, please give the Building Division a call directly at (970)
962-2505.
To
assist you in requesting inspections, we have created a list of inspection
types and their corresponding numeric computer codes. This list is
provided with new permits and is available upon request. When you call
the Inspection Request Line, (970) 962-2100 all you will need to submit, in
the following order, is the (1) Inspection Type(s) by number from the
list and (2) Permit Number. Please check that the correct
permit number has been provided.
|
NOTE! The building cannot
be used, occupied or furnished in whole or in part prior to receiving
a Certificate of Occupancy. |
|

No
furniture, people or stock can be placed in the building until a Certificate
of Occupancy is issued, unless prior arrangements have been made with the
Building Division. |