| Year of Creation |
1925 |
| Employees |
42.8 |
|
Rates |
|
| System Data |
|
| Net Generation |
2,746 MWh |
| Power Purchased |
676,931 MWh |
| Summer Peak |
125,314 MW |
| Winter Peak |
105,472 MW |
| |
|
| Distribution
(overhead) Pole Miles |
117 miles |
| Distribution
(underground) Circuit Miles |
459 miles |
|
Total |
576 miles |
| |
|
| System Load
Factor |
49.65% |
| System Power
Factor |
96.8% |
| |
|
| Generating
Units -
Hydro - Total Capacity |
700 kW |
| |
|
| Number of
Substations |
6 |
| Number of
Substation
Transformers (Plus
15.8 Mva capacity from WAPA at the Derby Hill Sub) |
11 (22 Mva each) |
| |
|
| Distribution
Voltages
(22 kV, 4.1 kV & 2.4 kV in
the canyon) |
12.4 kV |
| Customers |
|
|
Residential |
28,122 |
| Commercial
|
3,940 |
| Industrial |
337 |
|
Total customers |
32,399 |
| Average
residential rate |
7.151 cents/kWh |
| Average residential
power use |
9.44 kWh/ per capita/ per
day |
|
|
|
|
|