|
|
|
Timeline
1978 through 2004 |
1978
-
Completed
construction of existing Green Ridge Glade Reservoir following the
Big Thompson Flood in 1976.
1988
-
Completed
water supply study. Recommendations from Camp, Dresser and McKee,
Inc. included expanding the reservoir.
1989
-
Approved
by City Council that water rates be increased annually for eight
years to fund the expansion and cover water utility operations.
1990
-
Implemented
first of eight water rate increases.
-
Purchased
two parcels of land west of County Road 29 for possible reservoir
expansion.
1997
-
Required
environmental studies began that included studying possible
impacts of the expansion on wildlife, wetlands, cultural
resources, socio-economics, hydrology, and water quality. Signed
contact with Woodward Clyde Consultants to conduct a feasibility
study. Hall, Pitts and Associates started the environmental
assessment. A survey for the Preble’s jumping mouse was
completed.
-
Completed
the eight annual water rate increased in December.
1998
-
Conducted
public information meeting for the neighbors and general public.
1999
-
Larimer
County Planning Commission held a public hearing about the
relocation of County Road 29.
-
Held
a second public meeting for neighbors and interested citizens.
2000
-
Retired
water utility general obligation bonds.
-
Board
of County Commissioners decided to locate County Road 29 on east
side of reservoir and require noise level studies.
-
The
U.S. Bureau of Reclamation signed the final draft of the
Environmental Assessment with a Finding of No Significant Impact.
-
The
404 Permit from the U.S. Army Corps of Engineers was signed by the
City Manager.
2001
-
Started
working with a design consultant to prepare easement documents for
the reservoir spillway and northwest side of the reservoir.
-
Held
neighborhood meeting at Sylvan Dale Ranch to report on the
progress of the project and to identify concerns.
-
Met
with the Loveland Historic Society and State Historic Preservation
Office about the project because a small amount of land on a
historic site was involved in the expansion project.
-
Held
meetings with the Larimer County Board of Commissioners about
design changes that impacted County Road 29.
-
Completed
negotiating a long-term contract with the U.S. Bureau of
Reclamation and the Northern Colorado Water Conservancy District
to carry non-project water to the expanded reservoir.
-
Hired
consultant to provide third-party review for the State Water
Engineer’s Office.
-
Started engineering design
process.
2002
-
Started
95 percent design review in February.
-
Completed
construction drawings on September 30, 2002.
-
Issued
bid documents in October that contained a goal that at least 10
percent of the construction was to use local labor and resources.
-
Closed
bidding process in November with three contractors submitting
bids.
-
City
Council awarded the construction bid to SEMA Construction of
Englewood on December 17, 2002. The Loveland Utility Commission
and staff were delighted with the $13 million bid. The bid was
significantly lower than some of the early engineering estimates.
-
Drained
the reservoir for construction to begin.
2003
-
Construction
started on February 12, 2003.
2004
- Completed construction and dedicated
the newly expanded reservoir on August 27, 2004.
|
|
| If
you have questions about the construction of Green Ridge
Glade Reservoir, please contact Larry Howard, Project
Manager, at 970-962-3703 or send email. |
Send
us email
|
|