Loveland's Raw Water Supply
and the Expansion of Green Ridge Glade Reservoir
Beginning in 1887, the City of Loveland
diverted all of its municipal water supply
directly from the Big Thompson River. The City
built a pipeline into the water treatment plant at
Chasteen's Grove that provided high quality water for many decades.
Following the 1976 flood in the Big Thompson Canyon, when Loveland's
population was about 25,000, citizens supported additional protection
for the City's water supply. From this concern, Green Ridge Glade
Reservoir was built in the valley above the water treatment plant.
Since completion, the reservoir has provided about 600 acre-feet of
stored water to use in emergency situations. With the current
population of over 50,000 people, the reservoir will provide water for
about six days during the hottest part of the summer, if water use is
not curtailed.
The City Council established the water board on
December 16, 1980, to help guide the council in
decisions concerning the supply of raw water. The
water board recommended a study of the raw water
supply and a determination of the reliability of
the water supply during a drought. The Drought
Study was completed in 1988. Based on the study
results and the recommendations of the water
board, the City Council authorized purchasing
additional water supplies and expanding Green
Ridge Glade Reservoir. The additional water was
purchased in 1990. In 1989, the council approved
eight annual water rate increases starting in
1990. The funds from the rate increases were
allocated to expanding the reservoir, expanding
the City's raw water supplies, and paying for
departmental operations and maintenance. The last
water rate increase was in 1997.
Planning
Begins
In 1997, City Council directed staff to proceed
with formal planning for the reservoir expansion.
Studies completed the following year revealed that
the existing reservoir could be expanded to
approximately 6,000 acre-feet. The expansion would
provide enough emergency water to last about 60
days without implementing water use restrictions.
In addition, the expanded reservoir would allow
the City to store water from shares of water it
owns in several irrigation companies, which makes
the water available all year instead of only
during the normal growing season.
Environmental
Assessment
An Environmental Assessment (EA) was
performed for the Project by the U.S. Bureau of
Reclamation (Reclamation). Reclamation served as
the lead federal agency for the project, as
required under the provisions of the National
Environmental Policy Act. On June 9, 2000, a
Finding of No Significant Impact (FONSI) was
issued by Reclamation. This means that the
environmental commitments and mitigation to be
implemented by the City as outlined in the FONSI
and in the EA will minimize the environmental
affects of the project to the point that
Reclamation believes there will be no significant
impact on the human environment at the reservoir
site or downstream.
Other
Required Actions
Location and Extent Review. Larimer
County required that a Location and Extent Review
be conducted for the expansion project. In October
1999, the Larimer County Planning Commission
approved the review. On January 10, 2000, the
Larimer County Commissioners directed that the
portion of County Road 29 that will be inundated
by the reservoir be relocated on the east side of
the expanded reservoir. See
diagram for details.
404 Permit. To build the expansion, the
U.S. Army Corps of Engineers (Corps) required a
404 Permit. The permit was required because about
0.8 acres of wetlands along the inlet to the
existing reservoir and at the downstream toe of
the existing dam will be covered with water or
soil by the expansion project. On June 12, 2000,
The Corps issued Department of the Army Permit NO.
200080078 for the Green Ridge Glade Reservoir
Expansion Project. This will allow the
construction process on the expansion to proceed
once the final design is complete.
Basis of Negotiation. The City applied
to Reclamation to begin negotiations for a
long-term contract with Reclamation and the
Northern Colorado Water Conservancy District to
carry the City's native water through the federal
facilities. The local office of the U.S. Bureau of
Reclamation prepared the Basis of Negotiation
(BON) document that initiated the negotiation
process. The BON was submitted in the spring of
2000 to the Solicitor for the U.S. Department of
the Interior who ruled in July 2000 that Interior
did not have the authority to negotiate such a
contract under existing laws.
After the Solicitor's ruling, the City of
Loveland Water and Power Department had two
choices. The first choice was to seek a basis for
a long-term contract through specific legislation
for the expansion of Green Ridge Glade Reservoir.
The second choice was to include building a pump
station to transfer water to the reservoir.
On July 21, 2000, Senator Wayne Allard of
Colorado introduced legislation (S.B. 2906) that
would provide the requisite authority for the U.S.
Bureau of Reclamation to enter into a long-term
contract with Loveland to transfer the water to
the reservoir. Subsequently, Representative
Schaffer introduced the legislation (H.B. 4991) in
the House of Representatives.
The Senate and House of Representatives
attached the Allard amendment to the VA/HUD
Appropriations bill that was passed on October 19,
2000. the measure was sent to the President.
President Clinton signed the bill on October 27,
2000.
Now, the City of Loveland Water and Power
Department can initiate the necessary Basis of
Negotiation process with Reclamation to negotiate
a long-term contract with the City of Loveland for
transporting water from the Big Thompson River
through the Hansen Feeder Canal, owned by
Reclamation, to the expanded reservoir.
It is expected that the contract to transport
the native waters will be negotiated and completed
in early 2001. It is very likely that the contract
will be in place before the construction begins.
Engineering,
Design and Construction
All of the regulatory steps have been completed
except for the Basis of Negotiation with the U.S.
Bureau of Reclamation.
Final engineering and design work are
beginning, and are expected to take about 18
months to complete. Following completion of the
design work, the City will select a contractor,
negotiate a contract with the contractor, and
prepare to proceed with construction on the site.
If all current estimates hold, construction could
begin in 2002, with the expansion expected to be
completed in late 2003.
The expanded reservoir can be filled at
completion with Colorado-Big Thompson or Windy Gap
Project waters with no additional legal or
administrative changes.
Completion of the expansion of Green Ridge
Glade Reservoir, at an estimated cost of $20
million, will give Loveland's citizens an adequate
emergency supply of water. In addition, the
expanded reservoir will improve opportunities to
efficiently manage the City's raw water supplies.
Back to the top |